HomeMy WebLinkAboutMinutes_GTEC_09.20.2006Minutes of the Meeting of
Georgetown Transportation Enhancement Corporation
and the Governing Body of the
City of Georgetown, Texas
Wednesday, September 20, 2006
The Georgetown Transportation Enhancement Corporation of the City of Georgetown, Texas, met on
Wednesday, September 20, 2006.
Board Members Present:
Henry Carr- President, Joe Savage – Vice President, Farley Snell – Secretary, Paul Brandenburg –
General Manager, Micki Rundell – Finance Manager, Gabe Sansing, Ricki Salazar
Board Members Absent:
Pat Berryman, Henry Boecker
Staff Present:
Joel Weaver, John Aldridge, Joe Lara, Laura Wilkins, Jim Briggs, Tom Benz
Minutes
Regular Meeting
Board may, at any time, recess the Regular Session to convene in Executive Session at the request of the President, a
Board Member, the City Manager in his capacity as General Manager of the GTEC Corporation , the Assistant
City Manager, or legal counsel for any purpose authorized by the Open Meetings Act, Texas Government Code
Chapter 551, and are subject to action in the Regular Session that follows.
CALL TO ORDER AT
Meeting Called to order by Mr. Henry Carr, on Wednesday, September 20, 2006 at
2:00 p.m.
A. Consideration and approval of the minutes from the regular meeting held July 19, 2006. --
Paul E. Brandenburg
DISCUSSION: NONE
ACTION: Motion by Sansing, second by Snell to accept as written.
APPROVED 5-0 (Pat Berryman and Henry Boecker absent)
B. Discussion and possible action regarding the Project Progress Report and timelines
(including but not limited to items listed). -- Joel Weaver/Tom Benz
DISCUSSION: Updates presented by Weaver
IH 35 Frontage - Continue excavation on south end of project; bend caps complete and
poured; set beams mid-October (as of Friday's info.) Joel will get with Keith Hutchinson as
we get closer and put out a press release - TxDOT wants to shut down the two west lanes on
the Interstate to rig and swing the beams from the interstate (this will be a night time
project).
Lakeway Drive Overpass - Had a second utility coordination meeting in August with
TxDOT and CPY. Still waiting to receive some of the drawings from CPY - have the
locations and are in the process of verifying locations and any necessities for re-locating any
utilities. September 7, 2007 is still the anticipated bid letting date.
Wolf Ranch Parkway - Slow down due to rain. Contractor still says they will be done with
project on time. December 1, 2006 is the substantial completion date - final completion in
January, 2007. All ROW excavation and subgrades - complete. Base course has not begun -
delayed due to rain until next Monday , September 25. All Utilities are in and the main
excavation is complete. Question from Snell will the road be open by Thanksgiving? -
Answered by Weaver it looks favorable - but will not promise at this time. Chasco says that
they will complete on time (December 1) - but they are going to try to have open by
Thanksgiving.
Southwest Bypass - Project B and C - Discussions still on-going with the State for the pass-
through tolling portion. County Bond Program - this project did make the final cut as far as
what was voted on to include in the grant that the County will take to the voters.
Approximately $15 million is the latest estimate. Question from Snell - pass through toll
piece is to be included. Answered by Brandenburg TxDOT original study showed that it
was not eligible which means it will be December now which we had hoped to leverage the
money - but that changes our plans. That is why it is very important that we work with the
County on their bond program and that their bond program to give us at least that money
there. Jim stays in contact with bob Daigh at the State to press this issue. Comment from
Briggs - the consultant came with information that the state would like to see us move
forward in some way. Jim reviewed speed and traffic numbers in the area from Churchill
Farms over to IH 35 and back. Roughly 4,200 cars per day - including return trips. Indicates
that for the most part traffic in this area is commuter traffic. Only about 200 cars stay in the
area the other 4,000 are just passing through. This is working as a bypass. Question from
Carr - what did they think it was functioning as? Did they not read the data. Answered by
Briggs - they did not previously have the data - they just thought it was probably
functioning as a local roadway - but the data is clear that the road is working as a bypass.
Southeast Arterial 1: Geotechnical , environmental and archaeological testing are complete.
Graphic design is complete. Vertical and horizontal alignment are complete. Geometry of
elevated structures at the intersection of Interloop and under way. Final design is about
55% complete. We did take delivery on meets and bounds for the right-of-way this past
week. Aldridge is reviewing. There are a few minor changes to make to verbiage and then
we will begin securing the right-of-way.
Not included in packet - just got from CPY late - Park Central Blvd. off of Westinghouse Rd.
We do have a engineer's time line on this now. They are beginning with design
(geotechnical and survey) on their end. They plan to be ready to advertise for construction
in January, 2007 - receiving bids in March, 2007 and then award of bid in April, 2007 with
completion of construction in August, 2007. This is a basic timeline and we see some areas
where we can shorten if needed. Comment from Sansing - needs to be much shorter.
Weaver responded that he agrees - we did get the contract to them and they just sent this to
us. Basically, what they did is took original proposal and pushed out some of the dates and
we have not had time to discuss yet to shorten advertising from three months to a month,
etc. We will tweak these things - but just wanted to give the Board a heads up since we just
got the information back. Question from Carr - have we already awarded the contract?
Answered by Weaver - yes we have. Question from Carr - too late to take back? Answered
by Briggs these changes will be easily made internally and that is why we have Weaver and
Aldridge to manage these items. Aldridge stated that staff is scheduled to meet with CPY
soon and they will handle it. Question from Snell - will we need to dig it up and replace?
Answered by Benz - we will have to evaluate - but road is basically falling apart - we will
evaluate the subgrade too.
ACTION: NONE
C. Presentation of Georgetown Transportation Enhancement Corporation monthly financial
report for August 2006. -- Micki Rundell
DISCUSSION: Rundell presented the report. We are 81% of revenues this year as
compared to 73% at the same time last year. Page 5 - history report. For the year 26.1%
ahead of where we were last year.
ACTION: NONE
D. Discussion and possible action to approve the 2006/07 Interlocal Service Agreement between
GTEC and the City for administrative services, Micki Rundell, GTEC Finance Manager
DISCUSSION: Rundell presented the item. Administrative Services contract - 12,100/mo.
Bylaws - we will be bringing updates to the Bylaws later this year.
ACTION: Motion by Snell, second by Savage to approve.
APPROVED 5-0 (Berryman and Boecker absent)
Discussion before the vote - Question from Sansing. Are the rates different from last year?
Answered by Rundell - no, they are the same. Does that fact that there is now a
Transportation Advisory Board affect the amount of money that we anticipate spending
overall versus last year? Answered by Rundell - We did use some of the Transportation
Planning money and moved it to the General Fund and it is now a part of the GTAB budget.
Comment from Brandenburg - After we go one full year in GTAB we will be able to see how
much money we are using or not using and that is why this amount could possibly go down
in future years.
Motion to adjourn by Sansing, second by Salazar.
APPROVED (Berryman and Boecker absent)
Adjournment
The meeting was adjourned at 02:18 PM.
Approved : Attest:
_______________________ ________________________
Henry Carr - President Farley Snell - Secretary