HomeMy WebLinkAboutRES 880362 - Airport Grant Agmt-2
RESOLUTION NO. 9803
WHEREAS, the City Council (the "Council") of the City of Georgetown,
Texas (the "City") has accepted federal grant funds from the Federal
Aviation Administration (the "FAA") in order to improve facilities and
safety at the Georgetown Municipal Airport; and
WHEREAS, the City has contracted for the construction of the
rehabilitation of Runway 18-36 and the overlay of Taxiways A and C to
be funded by FAA Project No. 3-48-0093-02-88, accepted by the City on
September 30, 1988; and
WHEREAS, the FAA desires to amend this Grant Agreement by adding a
portion of the construction of the aircraft parking apron; and
WHEREAS, the amount of the Grant Agreement, $500,000.00, will remain
unchanged;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
GEORGETOWN:
Section I: That the Council hereby approves the amended Grant
Agreement, Project No. 3-48-0093-02-88.
Section II: That the Council hereby authorizes the Mayor to execute
the amended Grant Agreement, the City Secretary to attest to, and the
City Attorney to approve as to form.
Passed and Approved this eZ �, day of 1988.
Tim Kennedy, Mavorl
Approved as to Form:
DiA7ne CallaAder, City Attorney
NFAVWIIFIFIWN1�
TO: Mayor and City Council
-4/
FROM: Travis McLain, Airport Manager I
SUBJECT: Amendment to FAA Grant Agreements
The Grant Agreement that the City accepted from the FAA in
September, 1987, in the amount of $649,500.00, allocated
$280,000.00 of the grant to the construction of an addition to the
aircraft parking apron. However, the estimated cost of the
addition totals $376,809.00 (FAA 90%: $339,128.00)
The Grant Agreement that the City accepted from the FAA in
September, 1988, in the amount of $500,000.00, is for the
rehabilitation of Runway 18-36, and the overlay of Taxiways A and
C. The total estimated cost for this project is $424,428.00
(FAA 90%: $381,985.00).
The total amount of grant funds available for the two projects is
$780,000.00, and 90% of the total estimated cost of the two
projects is $721,113.00. By amending the two grants to delete a
portion of the apron work from the 1987 grant, and adding a
portion to the 1988 grant, the City will be able to complete both
projects within the budgeted amount of $952,000.00. Total
estimated cost for both projects is $801,237.00.
The FAA has requested that the City accept the two grant
amendments, which do not increase the amount of either grant. The
staff also recommends that the Council accept the two amendments.