HomeMy WebLinkAbout0365_360360
Paject Schedule Item
Submitted to State (TWQB)
Final Plans and Specifications Initiated
Completed
Date of Action
March 29, 1974
Immediately after
Grant Offer Received
60 Days After
Initiation
Submitted to State (TWQB) 70 Days After
Initiation
NOTE: All dates are subject to revision at the time of grant offer.
Advertise for Construction Bids within the days indicated after authorization
to advertise for bids has been issued 45 Days
Submit Bid Opening Documents within the days indicated after
the bid opening date 5 Days
Award Construction Contract within the days indicated after
authorization to award the contract has been issued 10 Days
Initiation of Construction within the days indicated after
the award of the contract 30 Days
Complete construction within the days indicated after initiation
of construction 425 Calendar
Days
Availability of Financing Funds for applicant's share
of the project costs May, 1974
Availability of the Site (s) for the project facilities Immediately
BE IT FURTHER RESOLVED that the above-named applicant understands that the
above project schedule must be approved by the Texas Water Quality Board and the En-
vironmental Protection Agency, and that once a project schedule has been approved, no
changes will be authorized without first receiving approval of the change from the Texas
Water Quality Board and the Environmental Protection Agency.
PASSED, APPROVED AND ADOPTED this 25th day of March, 1974, A.D.
ATTEST:
City Secretary oe E. Crawford, Ma i of Georgetown