Part 2. The following Sections of the Subdivision Ordinance are amended
by adding additional paragraphs as indicated:
Section 4 - PROCEDURE
4.01 7. e. Letter of certification obtained from the City Manager
as to whether or not the proposed development is in an
area subject to height zoning restrictions imposed by
the Georgetown -Williamson County Joint Airport Ordinances.
f. If proposed development falls in the area subject to
height zoning restrictions, developer will give written
assurances that height zoning restrictions will be in-
cluded in subdivision restrictive covenants and will
grant and indicate on the final plat avigation easements
over all platted areas with a height zoning restriction
of less than 150 feet. No lot or building area will be
permitted within a runway approach clear zone.
4.02 4. c. For Agigation Easements. All Final Plats which have
sites restriction imposed by the Georgetown -Williamson
County Joint Airport Ordinance of less than 150 feet
will clearly Indicate these restrictions as "avigation
easements" in a manner acceptable to the Planning and
Zoning Commission. Final Plats will also indicate the
extended centerline of the airport runway if the Plat is
within two miles of the end of the runway.
Section 5 - GENERAL REQUIREMENTS AND DESIGN STANDARDS
5.01 STREETS
20. Unpaved Street Right -Of -Ways. The portion of the street
right-of-way between a private lot line and the curb or
pavement edge shall be designed and constructed to meet
Engineering and Construction Standards established by this
ordinance or otherwise established by the City of George-
town.
21. Access to Public Streets From Private Property. Developers
or builders will not cut a curb or gutter section nor pave
a street right-of-way without first obtaining a permit
from the City Building Inspection Department, and comply
with the City of Georgetown Street and Curb Cut C•.finance.
Where no curb and gutter street construction is permitted
no developer or builder will construct or pave the bar
ditch street section without first obtaining a permit
from the, City Building Inspection Department and comply,
with the City Street and Curb Cut Ordinance. No temporary
utility service will be provided to the building lot or
site until a curb cut -street right-of-way permit has been
issued and no permanent utility service will be provided
until the work authorized by permit is satisfactorily
completed and approved by the Building Inspection
Department.
Part 3. The Engineer and Construction Standards established Im the Sub-
division Ordinance is amended by changing the "DRAINAGE AND STORM
SEWERS" to read as follows:
Drainage and Storm Sewers
Adequate drainage shall be provided within the limits of
the subdivisions. The protection of adjoining property
from any.increase in runoff is mandatory and shall be
considered in the review of the drainage and storm sewer
plans. Drainage and storm sewer plans shall be certified
by a Professional Engineer and checked by the City Engineer.